Hello all,

Hope someone had this issue on V12 before and will be able to help me understand it.


I've created a couple of MOs, and they are all stuck on a specific Work Order. It has been completed, but I get the message: "You can not change the finished work order."


At the same time I cannot close the MO, because I get the same error "You can not change the finished work order.".


In MO page it shows that 3/4 Work Orders have been done, even though the last one as I mentioned is completed. 


Has anyone had this issue before? 

What could be a possible solution for that?