Hi all

In Odoo 14 enterprise. Is it possible to calculate product process cost from the manual entered planned process time instead of the actual process time?


Regards,
Rickard

頭像
捨棄
作者 最佳答案

Ok so I found out how it works.

In product.product there is a smart button "Cost Analysis". This functionality is calculationg actual cost of: BoM+operations+scrap. However, in mrp.bom there is a another smart button "Structure & Cost". This one is calculation cost of: Bom+planned operation. The latter is also the one used for product cost and inventory valuation.

Hence, my problem wasn't really a problem :)