İçereği Atla
Menü
Bu soru işaretlendi
1 Cevapla
2509 Görünümler

Hi all

In Odoo 14 enterprise. Is it possible to calculate product process cost from the manual entered planned process time instead of the actual process time?


Regards,
Rickard

Avatar
Vazgeç
Üretici En İyi Yanıt

Ok so I found out how it works.

In product.product there is a smart button "Cost Analysis". This functionality is calculationg actual cost of: BoM+operations+scrap. However, in mrp.bom there is a another smart button "Structure & Cost". This one is calculation cost of: Bom+planned operation. The latter is also the one used for product cost and inventory valuation.

Hence, my problem wasn't really a problem :)

Avatar
Vazgeç
İlgili Gönderiler Cevaplar Görünümler Aktivite
1
Tem 25
976
1
Şub 25
4148
1
Ara 24
1663
3
Eki 23
3146
3
Nis 23
2918