Hello , i am using multilevel boms for manufacturing furniture . Each furniture is made by several pieces with several kits that connect and make my final piece of furniture , so the question is. Why when i make a manufacture order and i don’t have enough materials ,for example wood pieces for the drawer kit and metal pieces for the metal base ,i get notified i don’t have enough components but the production from the needed materials doesn’t start. I mean that , cant the odoo send a notification to have the needed materials produced? Because inside the kit of the drawer the is a bom about how the wooden parts need to be proceeded and prepared .So what happens when i dont have enough materials from my final product? Have i have to always check manually and manually produce the components missing from my furniture bom or there is an automated way so when i create a PO ,if needed ,the production of the materials is going to start ? I hope my description is not confusing enough . 

 

Аватар
Відмінити
Найкраща відповідь

Yes, if replenishment rules are defined and set to ‘Auto’ an MO for unavailable components would be generated.

Inventory > Operations > Replenishment menu to define product specific rules

Аватар
Відмінити
Related Posts Відповіді Переглядів Дія
1
вер. 25
1176
0
лип. 25
689
0
бер. 25
1188
0
бер. 25
1202
1
бер. 25
3101