If I have 10 manufacturing orders. I want to schedule priority of manufacturing orders from MO 1 to MO 10 in sequence but for order number MO 5, I found 10 parts are not available due to those components already reserved some in MO 6 and MO 8. Do I have to check manually each comp in MO5 as for which future MO is those components reserved? Can we automatically unreserve from other future MOs because my first priority is MO5 and not MO6 or MO8

Awatar
Odrzuć
Najlepsza odpowiedź

It's easy in V14  to unreserve component from manufacturing order list view by selecting MO and go to action and unreserve.

In case of this unreserve action is not available in your database then you can copy from demo database and create the same server action in your database.

https://youtu.be/NrY7uh3DJXo


Awatar
Odrzuć
Autor

thank you sir