If I have 10 manufacturing orders. I want to schedule priority of manufacturing orders from MO 1 to MO 10 in sequence but for order number MO 5, I found 10 parts are not available due to those components already reserved some in MO 6 and MO 8. Do I have to check manually each comp in MO5 as for which future MO is those components reserved? Can we automatically unreserve from other future MOs because my first priority is MO5 and not MO6 or MO8
Odoo is the world's easiest all-in-one management software.
It includes hundreds of business apps:
- CRM
- e-Commerce
- Comptabilité
- Inventaire
- PoS
- Project
- MRP
Cette question a été signalée
1
Répondre
3710
Vues
It's easy in V14 to unreserve component from manufacturing order list view by selecting MO and go to action and unreserve.
In case of this unreserve action is not available in your database then you can copy from demo database and create the same server action in your database.
https://youtu.be/NrY7uh3DJXo
thank you sir
Vous appréciez la discussion ? Ne vous contentez pas de lire, rejoignez-nous !
Créez un compte dès aujourd'hui pour profiter de fonctionnalités exclusives et échanger avec notre formidable communauté !
S'inscrirePublications associées | Réponses | Vues | Activité | |
---|---|---|---|---|
|
1
févr. 23
|
3450 | ||
|
0
avr. 23
|
3801 | ||
|
0
sept. 22
|
2794 | ||
|
2
avr. 19
|
5620 | ||
|
0
avr. 23
|
2277 |