In my calendar view all manufacturing orders are confined to a one hour slot. How can I change this

  • How can I change the length of the manufacturing order to three or four hours? When I drag the manufacturing order box down to increase the length it just jumps back to the one hour slot after releasing the left mouse button.

  • I would like to change the production time of a manufacturing order in a product specific way. Product A: 3 hours; Product B:1 hour. Is there an option to do this?


アバター
破棄
最善の回答

open the developer mode and choose edit calender view  and look at the fields that

effect on the order planning period .

you see they mention 'date_start' which it indicate the begin of the period but there is no 'date_stop' .

if you want to change that just add  the property of 'date_stop' and you will be able change the period of the order.