In my calendar view all manufacturing orders are confined to a one hour slot. How can I change this

  • How can I change the length of the manufacturing order to three or four hours? When I drag the manufacturing order box down to increase the length it just jumps back to the one hour slot after releasing the left mouse button.

  • I would like to change the production time of a manufacturing order in a product specific way. Product A: 3 hours; Product B:1 hour. Is there an option to do this?


Avatar
Abbandona
Risposta migliore

open the developer mode and choose edit calender view  and look at the fields that

effect on the order planning period .

you see they mention 'date_start' which it indicate the begin of the period but there is no 'date_stop' .

if you want to change that just add  the property of 'date_stop' and you will be able change the period of the order.