Hi everybody,

I have to manager a project during three years. I define all tasks but gantt view is difficult to read. Is it possible to compress view by year?

 

Avatar
Ignorer
Meilleure réponse

Try to install gantt_improvement from https://github.com/stephane-/Odoo-addons

In the gantt view click on Zoom-out and Zoom-In to navigate by Year, Month, Week, or Day.

Avatar
Ignorer
Auteur

I saw it but it is only for master branch. Is it avalaible for v7?

Yes, it's for V7.0

Auteur

Thank!! You right. It is working