On OE 16 for each BOM on the Miscelaneous Tab you have the option to make the manufacturing order when all components are ready or when components for the first operation are ready.

I could not find any way to tell the system which components belong to which operation

Any suggestion is welcome

Regards

Maurice

Avatar
Descartar
Mejor respuesta

Also looking for this info..?

Found it is set on the BOM component tab, by using the modify list view option to Consumed in Operation, then editing that field.