Hello! Good day to all of you!

I have a product (P1) with the following BoM: 1 P1 = 1 P2 + 12 P3

And in my stock I have 5 P2s and 16 P3s.

When I confirm a sales order for 2 P1s, it automatically creates a manufacturing order for 2 P1s because I have installed mrp_jit. And that MO record displays as 'Awaiting Raw Materials'. That is clear as I need 24 P3s to produce 2 P1s and I have only 16 P3.

My question is, do I have any method see that I have only 16 P3s (qty on hand) and that I need to purchase 8 more P3s to complete this MO, without going back to products list?

Thank you.

 

 