Hello everyone,

I am stumped on how to get Odoo to properly schedule my company's manufacturing. My company is a beer brewery that produces a large batch of beer (through 3 steps), then fills kegs from that large batch.

I created 2 products: the bulk beer (UoM="batch"=310 gallons; "batch" is in the volume category) and the keg of the beer (UoM is "unit(s)".

  • The kegs are Make to Stock- they are managed by orderpoint to maintain an inventory level to be sold. The BOM consists of 5 gallons of bulk beer and an empty keg.
  • The bulk beer can only be produced in a single batch size. Because of this, it is a Make to Stock product with the following orderpoint:

Minimum Quantity 0.00 batch

Maximum Quantity 1.00 batch

Quantity Multiple 1

  • It is manufactured in 3 steps:

 

Step 1 (one machine that takes 10 hours to complete a batch):

Capacity Information

Efficiency Factor 1.00

Capacity per Cycle 1.00

Time for 1 cycle (hour) 10:00

Time before prod. 00:00

Time after prod. 00:00

Step 2 (4 machines operating in parallel; each machine can process 1 batch from step 1 every 10 days; i.e. four batches from step 1 can be processed simultaneously):

Efficiency Factor 1.00

Capacity per Cycle 4.00

Time for 1 cycle (hour) 240:00

Time before prod. 00:00

Time after prod.00:00

Step 3 (one machine that takes 3 days to complete its work):

Efficiency Factor 1.00

Capacity per Cycle 1.00

Time for 1 cycle (hour) 72:00

Time before prod. 00:00

Time after prod. 00:00

Here is the routing:

Sequence/Name/Work Center/Number of Cycles/Number of Hours:

0/Brew/10bbl Brewing System/1.00/24.00

1/Fermentation/Fermentation Suite/1.00/240.00

2/Brite10bbl/Brite Tank/1.00/72.00

The keg orderpoint is for 30x kegs of this product, which is equal to 150 gallons or .484 batch. The MRP scheduler result is the following:

Sequence/Work Order/Work Center/Number of Cycles/Number of Hours/My comparison to reality

0/Brew - Beer/Machine 1/2.00/40:00 ---> 2x the correct cycles, 4x the correct time

1/Fermentation - Beer/Machine 2/1.00/480:00 ---> correct cycles, 2x the correct time

2/Brite - Beer/Machine 3/2.00/288:00 ---> 2x the correct cycles, 4x the correct time

 

Can anyone assist me in correcting the issue with incorrect cycles and times? Thank you.

Ảnh đại diện
Huỷ bỏ
Bài viết liên quan Trả lời Lượt xem Hoạt động
0
thg 10 21
8190
1
thg 1 24
2137
2
thg 3 25
6041
2
thg 2 22
11413
2
thg 4 24
6970