2782 Lượt xem

Creating a routing in a BoM.

The documentation says:-

You may define the work operation or step in which each component is consumed using the field, Consumed in Operation under the Components tab. Similarly, you can define the operation at which the product will be produced under the Miscellaneous tab using the field Produced at Operation. If this field is left blank, the products will be consumed/produced at the final operation in the routing.

BUT - version 10 does not have a "Produced at Operation" field - please explain or help...

Ảnh đại diện
Huỷ bỏ
Tác giả

Do you have an update on this for me, please?