Hello everyone,


I would like to use MPS to manage replenishment for a product with a very long Bill of Materials (around 100 parts). 

If I'm correct, the replenish green button on top of the MPS is launching a RFQ for every products that needs to be replenished today by taking account of delivery leadtime. But in my case, I would like to launch a RFQ for all the products to replenish, regardless of lead time. 

I can start replenishment regardless of lead time by manually clicking on the replenish button in every product line, but it's quite tedious with a long BoM. Is there a way to automatically launch all replenishment ?


Here's an exemple :

Product 1 : To be manufactured

BoM of Product 1 :

  • 1x Product A, Buy Route, 5 days of delivery lead time, 0 in stock
  • 1x Product B, Buy Route, 2 days of delivery lead time, 0 in stock

10 Product 1 needs to be manufactured in 5 days (quantity entered in forecasted demand line)

Suggested replenishments :

  •  Product A : 10 units to replenish today
  •  Product B : 10 units to replenish in 3 days

If I click on the replenish top button, only a RFQ for Product A will be launched. But I also want to have one for Product B.


Thanks !