Is there any way to automate step tasks in projects? Where does the next step automatically change state when its predecessor completes?
Thank you very much in advance!

Avatar
Zrušiť
Best Answer

With the standard application, there is no way to Change state tasks automatically, you can do this through special modifications

Avatar
Zrušiť
Autor Best Answer

I'm using Odoo Community Edition 15. Where can I make changes?