In our manufacturing MPS, I can't replenish for each month. When I click replenish again and again it replenish only that particular month.  I want to replenish for every future month

Avatar
Annuleer
Beste antwoord

If your Master Production Schedule (MPS) is not generating Manufacturing Orders (MOs) for future months, here's what to check:

  1. Forecast Dates
    • Ensure the forecast date range includes the future months you expect MOs for.
  2. Minimum/Maximum Quantity Rules
    • Check if the Minimum To Replenish is set correctly for those future dates.
  3. Replenish Button
    • MPS does not auto-generate MOs. You must click "Replenish" manually (or automate via scheduled actions).
  4. Product Settings
    • Make sure the product is set as Manufacture and has a proper BOM (Bill of Materials).
  5. Scheduled Actions
    • In Odoo Enterprise, the MPS can be automated through scheduled actions. Ensure it’s active.

If you’re using Odoo Online (SaaS), the ability to automate replenishments is limited, so manual triggering might be necessary.

At Wan Buffer Services, we often help manufacturers configure MPS rules for seasonal demand and longer planning cycles. Let us know what version you're using and your planning frequency—happy to suggest an optimal setup.

Avatar
Annuleer
Gerelateerde posts Antwoorden Weergaven Activiteit
1
aug. 18
3440
0
okt. 16
4171
0
dec. 20
3282
2
mrt. 17
4868
4
feb. 24
10554