Skip to Content
Menu
This question has been flagged
1 Atsakyti
4955 Rodiniai

I would like to know if OpenERP 7.0 supports Critical Path Monitoring (CPM). If yes how? Can you point me to a reference?

Tnx.

Portretas
Atmesti
Best Answer

You can do that with the community modules "project_time_sequencing" and "project_time_scheduling"

Portretas
Atmesti
Related Posts Replies Rodiniai Veikla
1
kov. 15
5673
2
kov. 15
10175
0
kov. 15
3844
0
kov. 15
5036
1
kov. 15
4997