Hello,

We are using the manufacturing app to build PCs.

Our work flow is to pick the components needed based on the BoM, register the serial or lot number and then assembly them together.

Those operations are done at the same work center.

The problem is, if we configure the operations in that order : components registration and then assembly, Odoo only allows us to register consumption during the last operation.

Which is awkward for the operator since it does not reflect what he does in real life.

Do you have any idea on how we could optimise this flow ?

We tried to use steps in the operations, work with different work centers but it did not help either.


Thank you.


Julien

아바타
취소
베스트 답변

In the BOM you can assign components to what operation you want them to be consumed.

You can also have several operations with the same work center.  Each operation will have a separate work order.  I am not sure if you will find the way to work optimised, but might get you on the way,

아바타
취소
작성자

Thank you Lars, assigning components to the operation worked !