We have a few potential customers who use the stock_planning (Master Procurement Schedule) module in OpenERP v6.1. But unfortunately, this module is not available for OpenERP v7.0 any more. Will the OpenERP have any plan to make this module available in the next version eg. v7.1?

아바타
취소

Same here. Could someone give some information about the migration of this module to v7.x?

Versions 8 and 9, even!

베스트 답변

You should port the module to v7, it is not a big deal to do that

아바타
취소

Why does OpenERP SA was not able to port it then? IMHO this is a very important module. We need it also for our client

베스트 답변

for V7.0  download it from: http://bazaar.launchpad.net/~credativ/credativ-openerp/addons-7.0/

 

Thanks to Credativ.