I'm having some trouble routing my stock in a configuration with two manufacturing locations.  My manufacturing plant is a brewery.

  1. Manufacture wort in the brewhouse, put it in a tank in the cellar

  2. Add more ingredients in the cellar, manufacture finished beer

A manufacturing order for step 1 goes as planned.  The wort goes into the cellar. When I create another manufacturing order for step 2 it is held up awaiting raw materials.  A stock move for the extra ingredients is generated for Cellar -> Production, but not for Warehouse/Stock -> Cellar.

How do I automatically get stock from the Warehouse to the Cellar?

아바타
취소

I'm in the wine business and would love to connect with you. Did you solve this question? How do you account for waiting during production? i.e. fermentation