Dear All,

I have a product with many subassemblies (multi-level BOMs); meaning Product A consistes of B, B consistes of C, C consistes of D and so on; The creation of all MOs works, but I would like to consider available stock at any location before a MO is created. Means, when I already have 100 of B, I won't need the MO for Product B and below, but the MO for Product A just takes the stock of Product B.

Any idea how I can set up the routing that available stock is considered?

Thanks in advance!

Philipp

아바타
취소

Philipp,

Did you ever figure this problem out?  We are on Odoo 13 and headed towards Odoo 16 but it doesn't appear that Odoo 16 can handle multi-level BOMs with values/attributes in the 2nd level.

베스트 답변

You can consider your product as a Make to Stock so it will always check stock first. And if stock haven't enough stock it creates related MO or PO, ...
Documentation : Documentation 