I need to plan production by allocating specific tasks to specific workstations and specific people within workstations. Using standard durations for specific tasks, I would like to see how much more capacity I have per individual and per workstation. At what stage should I expect to make use of additional labour i.e. over-time etc.? This information can help me to communicate more accurate lead times to my clients and monitor the productivity levels per individual and for the factory overall. 

Is the Manufacturing Module the right option for this requirement, and to what extend can it fulfil the same, please?