Hi, I am using 3 step manufacturing, and MTO route.

I sometimes register SO with future delivery dates, so I want to set the raw materials reservation to be done about 7 days before the start date of the production.

My question is: 

In operation types, I have "Manufacturing" and "Picking Components".

In both operations I must select a reservation method from the 3 types (Manual, On confirmation, or Before scheduled date reservation)

I don´t know what is the right configuration, for each one. In which one should I set "the 7 days before" and how should the other operation type be configured?


Thank you!

アバター
破棄
最善の回答

I am also facing the same situation when manufacturing under MTO. Have you tried setting ‘Before scheduled date reservation’ for Picking Components?

アバター
破棄

Because usually the raw materials will be taken out before starting MO, and in the Manufacturing step, only On confirmation is needed. Have you tested it in practice?

This post was last modified: 12-09-2025, 03:58 am by https://geometrydash22.com

最善の回答

Hi,

You should set 7 days before on Picking Components, and leave Manufacturing as is (probably At Confirmation). Materials for picking will be reserved 7 before scheduled manufacturing start (based on Manufacturing Lead time).

This might help:

Best Regards,

Dawid Gacek, Adapt IT