Hi,

I'm using Odoo 18, and I want to calculate the costs and time based on employees available on a work center.

For example, a work center capacity is 10 employees, but 2 of them are absent today so the capacity today is 8 employees, how should I manage that, so Odoo calculates the correct time and costs today.

I only see the capacity as total of employees, or should I change the capacity of a work center each day? Is it a good practice?

Avatar
Abbandona
Risposta migliore

I have calculated a reasonable time to execute the new game

Avatar
Abbandona
Risposta migliore

the current option available in Odoo is that it will calculate the cost and time based on actual execution of MO by using the resources (employee assigned to workcenter) you have, but your question is about calculating based on configuration / employee attendance, which can only be done with customization

Avatar
Abbandona
Risposta migliore

I was wondering the same, maybe we reach the same conclusion, that we can't?

Regards.