Components for 2-step manufacturing are located in three different warehouses. What settings should be made so that they are written off to one manufacturing order? We created a transit warehouse as a parent, but this setting is constantly lost. Maybe the location should not be transit but viewing? Please help me figure it out.

Avatar
Abbandona
Autore Risposta migliore

Hello Lars,

Thank you for your response!

I’ve solved this by using a virtual warehouse. Thank you for your help!

Best regards, Nina.

Avatar
Abbandona
Risposta migliore

You will have to transfer from the components warehouse into the manufacturing warehouse, before you can consume in the manufacturing order. 

As standard you will have three steps: Send from one warehouse into transit. Receipt in the other warehouse. Picking to manufacture order into pre production.

By modifying the routes you can put all into one step: Just send from one warehouse and automatic receive into pre production.