Skip ke Konten
Menu
Pertanyaan ini telah diberikan tanda
1 Balas
3117 Tampilan

Hello,

How can I automate the status update of a parent task?

I would like the parent task to be updated to "done" when all its blocking subtasks are done.

Is it possible?

Thank you for your help!

Avatar
Buang
Jawaban Terbai

You could try this:

Settings > Techincal > Automated Actions:

Model: Task
Trigger: On Update
Trigger Fields: Blocked By
Before Update Domain: Blocked By > Stage > Name = "in progress"
Domain: Blocked By > Stage > Name = "done"
Action To Do: Update the Record

Data to Write:
Field: Stage (project.task)
Evaluation Type: Reference
Record: Done

Avatar
Buang
Post Terkait Replies Tampilan Aktivitas
2
Mei 25
1062
1
Apr 20
2638
2
Sep 23
3518
2
Mei 17
8190
2
Mar 24
2589