Skip ke Konten
Menu
Pertanyaan ini telah diberikan tanda
3827 Tampilan

Hi!

When we start the procurement manually (Version 7), the dates of all quotations are set to today.

But what we want is, to set the date to "start of production - delivery time - security days".

We don't want to fill our warehouse in next days (today + delivery time), when the production of the product is going to start in a year ...

Is it a bug or what are we doing wrong?

Thanks!

Avatar
Buang
Post Terkait Replies Tampilan Aktivitas
5
Feb 24
13143
1
Mar 15
4749
4
Mar 15
29590
1
Mar 23
23872
1
Jul 16
11376