Hi,

I face a problem regarding planning of fabrication. How can I plan a MO depending on the work center's capacity ?

For ex. A MO needs 40 h and on the next week I have 50h available ?

If it's not possible in standard, do you know add on to complete this lack of functionality ?

TIA 