Hello, in my manufacturing process sometimes I reuire to make changes in my design because of a change the customer have requested. Is there a way to update the bill of material and that will update the manufacturing order products after the MO have been in the confirmed stage?

Avatar
Ignorer
Meilleure réponse

See the section Draft MO on confirming SO at https://www.odoo.com/forum/help-1/how-to-configure-customizable-boms-in-odoo-247458

Avatar
Ignorer
Meilleure réponse

As far as I know, it is not possible after it has been confirmed.  You have to cancel it and create a new one.