In odoo 15, any time I create a work order, the status by default is "waiting for another wo" and the starting date is replanned to the end of the previous work order. I want to have my WO running in parallel and by default in ready state. I don't want odoo to reschedule dates for the new work orders.
Odoo is the world's easiest all-in-one management software.
It includes hundreds of business apps:
- CRM
- e-Commerce
- Kirjanpito
- Varastointi
- PoS
- Project
- MRP
Tämä kysymys on merkitty
1
Vastaa
2662
Näkymät
Thanks @Cybrosys, but that did not work for me.
Just as a reference, I solved the problem by:
Changing the default value from "Waiting for another wo" to "ready" and
redefining the following compute methods
date_planned_start = fields.Datetime(
compute=lambda self: self._compute_date_planned_start(),
default=lambda self: self._default_date_planned_start(),
string='Planned Start',
)
date_planned_finished = fields.Datetime(
compute=lambda self: self._compute_date_planned_start(),
string='Planned End',
)
Nautitko keskustelusta? Älä vain lue, vaan osallistu!
Luo tili jo tänään nauttiaksesi yksinoikeusominaisuuksista ja osallistuaksesi mahtavaan yhteisöömme!
RekisteröidyAiheeseen liittyviä artikkeleita | Vastaukset | Näkymät | Toimenpide | |
---|---|---|---|---|
|
0
elok. 24
|
1555 | ||
|
1
toukok. 24
|
2044 | ||
|
0
toukok. 24
|
1564 | ||
|
2
helmik. 24
|
2097 | ||
|
2
maalisk. 23
|
2607 |
Hi,
Please refer to this forum answer: https://www.odoo.com/forum/help-1/workaround-to-how-to-manage-operations-in-parallel-in-the-same-work-center-205360