There is an interesting quiz I found under the "MRP - Manufacturing & Shop Floor"/

Manufacturing Steps

1. How many manufacturing steps should I use to record the transfer of finished products to inventory?

Four

The correct number is displayed to be (3)Three.

It is quite interesting why it is like that? I was under the impression that they are (2)Two.


Thanks,

Petko

Avatar
Verwerfen
Beste Antwort

Hello, you can use 2 or 3. It depends on how you want to handle the finished products. Do you store them after they are manufactured, or do you send them directly for delivery?