My use case is the following; I'm running a bakery and I produce cakes but each cake is different

I will buy butter and flour and then produce cakes

But cake 1 will maybe require 1 kg butter and 2 kg flour while cake 2 will require 1,5kg butter and 2,5 Kg flour and so on

Then the "BOM" is never the same for each cake

How can this be handled with Odoo ?

Regards

Maurice

Avatar
Verwerfen
Beste Antwort

Hi Maurice,

Perhaps one of these modules may help you:

https://www.odoo.com/apps/modules/12.0/mrp_production_draft/

https://github.com/OCA/manufacture/tree/11.0/mrp_production_request/

If you want to make some changes to the MO (Routings, BOM, etc), you cannot confirm it until the changes are made.

-make

Avatar
Verwerfen
Autor Beste Antwort

The problem I'm facing is that in Odoo a BOM has to be defined before you can create a Manufacturing Order while in my context the BOM has to be defined at the same time as when the Manufacturing Order is created to produce the specific product

I will have a lokk at those modules : https://github.com/pledra/odoo-product-configurator

Avatar
Verwerfen
Verknüpfte Beiträge Antworten Ansichten Aktivität
2
Juli 23
7706
0
Juni 25
1836
0
Juni 21
2665
2
Okt. 17
4000
3
Sept. 16
7495