what is the deferent between PO and RFQ?

Avatar
Kassér
Bedste svar

HI,

In the simplest way, we can say RFQ is draft record and PO is confirmed records. RFQ's are quotations we have received from the supplier for a intended purchase and as there can be multiple RFQ's from different suppliers, we will select one among them, which is best for us and it will be confirmed as a PO.

Thanks & Regards

Avatar
Kassér
Bedste svar

an RFQ  is like a shopping list sent to multiple suppliers, asking them to give you prices for the items you need and A PO  on the other hand, is the actual agreement you place with a chosen supplier to purchase those items at a specific price and terms.

Avatar
Kassér
Bedste svar

What if I already know the price of the items being ordered? I just want to write a PO and send to The vendor. 


Currently its creating and RFQ, how do I skip the RFQ and just write a PO?

Avatar
Kassér

Hey, did you find a solution for that ? I have exactly the same need
Thanks in advance

Bedste svar

RFQ is an enquiry/request to vendor to provide information related the items wanted to buy, PO is the deal document to buy including items data, requirements and any condition related.

Avatar
Kassér
Bedste svar

RFQ is a request for quotation you sent to the supplier , while PO is a purchase order to the supplier after you check the prices sent from the supplier , at that time you can confirm your PO.