This question has been flagged
4464 Zobrazení

When SO is confirmed with due date set to next month (for example) Procurement is generated PO with earliest possible date (today + supplier lead). I'm expecting procurement date as late as possible: SO due date - supplied lead time.

Having a lot of SO confirmed to a 1st day of each month is leading to massive purchase scheduled to beginning of the year instead of gradual spread across the year.

I was trying to find scheduler range days parameter which was stated in v7 doc but had no luck.

Product is MTO, reordering rules are set, no realtime scheduler.