In the manufacturing app, "Planning by Production" view, I can reschedule work orders by dragging them to different timeslots.

I'd like to do this at the MO level so that the entire MO can be shifted to a different timeslot. Is this possible?

Avatar
Zrušit
Nejlepší odpověď

In effect what you trying to achieve is to change the 'scheduled date' of a MO. You can drag and drop to change it while on the calendar view of Operations > Manufacturing Orders menu

By doing so it does change the MO to an unplanned state.