hi,

All of the stock movements are done (included sub contractor), how to invoice  a PO accidentally cancelled ?

Now its status is RFQ, if a new confirmation is done, what about stock movements ?

TIA for help


Avatar
Descartar
Best Answer

Hi,

If the Purchase order has done, then cancelled, in this case already created transfers will cancel automatically, then it will create again after re-confirmation. So it will not effect the stock movement.

The cancelled and shipment after re-confirmation of purchase order will appear like below.


Regards