I would like to know how to set up procurement rules for the following situation:

1. Manufacturing a "Product" that consists of a "Part" with a single vendor with the delivery lead time of 10 days.

2. I will set up manufacturing for 1st week of June '18, 1st week of Sept '18 a' 50pcs

I would like to get 2 procurements (one in mid-June and one in mid-August) with 50pcs each

Currently, I cannot achieve this with either procurement rules or MTO, please help...

形象
丢弃
最佳答案

in v10 or v9 there is one module stock_calendar may be that will help you to schedule..

形象
丢弃